Episode Details
Back to Episodes
Battle Ground's 92nd Ave Closure: A Sewer Problem a Year in the Making
Published 19 hours ago
Description
A six-week utility project on 92nd Avenue in Battle Ground has stretched nearly a year after city inspectors found problems along the entire length of the newly installed sewer line, forcing the contractor to remove and replace the pipe. Battle Ground City Engineer Ryan Jeynes explains what went wrong and what comes next before the road can be paved and reopened. https://www.clarkcountytoday.com/news/sewer-line-problems-to-blame-for-extended-92nd-avenue-construction-in-battle-ground/ #BattleGround #ClarkCounty #SewerLine #RoadClosure #WashingtonState #Construction #Transportation #LocalNews