WindQuest Advisors on Repowering and Rising O&M Costs

WindQuest Advisors on Repowering and Rising O&M Costs

Published 1 week, 5 days ago
Description

Dan Fesenmeyer, Managing Partner at WindQuest Advisors, joins to discuss the repowering rush and the FAA permitting stall, rising O&M costs on larger turbines, tariff pass-throughs, and AI data center demand.

Sign up now for Uptime Tech News, our weekly newsletter on all things wind technology. This episode is sponsored by Weather Guard Lightning Tech. Learn more about Weather Guard’s StrikeTape Wind Turbine LPS retrofit. Follow the show on YouTubeLinkedin and visit Weather Guard on the web. And subscribe to Rosemary’s “Engineering with Rosie” YouTube channel here. Have a question we can answer on the show? Email us!

Welcome to Uptime Spotlight, shining light on wind energy’s brightest innovators. This is the progress powering tomorrow

Allen Hall: Dan, welcome back to the podcast. 

Dan Fesenmeyer: It’s great to be here. Great to see you again. 

Allen Hall: There is so much happening in your particular area. Your name pops up quite a bit within Weather Guard because, uh, we’re dealing with a lot of operators and- A number of times we’ll ask them, “Have you read your turbine supply agreement?”

“No.” “Have you read your full service agreement?” “No.” “Well, maybe you should do that.” And then we say, “Have you talked to Dan? You should call Dan, ’cause he can help you understand what you have signed.” Mm-hmm. “Oh, that’s probably a good idea.” So now that you’re here, WindQuest Advisors, of course, obviously is your company.

Mm-hmm. And you’re talking to a number of operators. The, the big hurdle at the minute, the nearest short-term hurdle, is repowering. There’s just a lot of [00:01:00] repowering efforts going on- Mm-hmm … trying to get turbines in, start a project. There’s a July 4th deadline and an end of the year deadline. There’s a couple deadlines after that.

What are you seeing right now from operators i- in terms of repowering? What’s the effort happening? 

Dan Fesenmeyer: Well, there was a ton of effort to start physical work. That window’s obviously closing- 

Allen Hall: Yes … 

Dan Fesenmeyer: very quickly, but it’s still open. Uh, and then once you’re past that window, my understanding is if you get your repower completed by the end of ’27, you didn’t really need to have started physical work.

But I think most folks, start physical work is kind of the insurance piece of it- 

Allen Hall: Sure … 

Dan Fesenmeyer: if things take longer. Uh, another thing that’s popped up is obviously FAA and other permitting. 

Allen Hall: On the permitting side, from the federal’s, uh, standpoint, is that stopped? Or, or are projects able to continue putting turbines in the ground, or what’s the status?

Dan Fesenmeyer: M