Metro Vancouver, Acciona Settle Wastewater Plant Dispute
Description
Metro Vancouver and Acciona settle North Shore wastewater plant lawsuit, with Acciona paying $235M to avoid further legal battles. The plant, initially costing $700M and set to finish by 2020, now stands at over $3B and wont be completed until 2030. The settlement paves the way for an independent project review to ensure transparency as the work progresses towards the new deadline.