Back to EpisodesVineyard Wind Sues GE, Ørsted Overhauls Its Board
Description
Vineyard Wind sues GE Renewables to block a walkout over $300M in withheld payments and defective blades. Plus Ørsted posts a $262M quarterly loss and shakes up its board.
Sign up now for Uptime Tech News, our weekly newsletter on all things wind technology. This episode is sponsored by Weather Guard Lightning Tech. Learn more about Weather Guard’s StrikeTape Wind Turbine LPS retrofit. Follow the show on YouTube, Linkedin and visit Weather Guard on the web. And subscribe to Rosemary’s “Engineering with Rosie” YouTube channel here. Have a question we can answer on the show? Email us!
Uptime316
Matthew Stead: [00:00:00] The Uptime Wind Energy Podcast brought to you by Strike Tape, protecting thousands of wind turbines from lightning damage worldwide. Visit strike tape.com And now your hosts.
Allen Hall: Welcome to the Uptime Wind Energy Podcast. I’m your host Allen Hall, and I’m here with Matthew Stead and Rosemary Barnes who are in Australia. Before we get too far into this episode, I would like to mention that the UK US relationship has been very tense recently, as you have seen in the, in the news articles and on television.
But there was one good news piece that just happened, which is the band Oasis just got inducted into the Rock and Roll Hall of Fame. So that is trying to mend those relationships, bring the UK and US back together. In at least a musical sense. So I know Rosemary was watching that closely as the votes were counted.
But, [00:01:00] uh, everybody in the UK is super thrilled about it as they should be. And all us Oasis fans can’t wait for the induction ceremony. In fact, we’re planning to go to Cleveland. They’ll go watch it if we can. We shall see now onto more important information this week. Vineyard, wind and GE are not getting along.
And if you have been paying attention for the last two years, you would’ve noticed that there’s been a couple of tense moments. Well, uh, that wind project is a little bit up in the air because vineyard wind has filed suit against GE renewables to stop the turbine maker from walking away after GE sent a termination notice.
Over a $300 million ish, uh, disagreement in unpaid bills. At the center of this dispute are defective blades, of course, that, uh, broke off in 2024 and caused a number of problems, uh, for GE and vineyard Wind is particularly a delay in the [00:02:00] project and ge having to fix pull blades off of turbines that were already installed and I think they ended up sending those back to France.
Reading the lawsuit, it seems like GE did not repair those blades. They replaced those blades because, uh, they may not have been able to repair them or maybe is the amount of time it’s gonna take to repair them. You can repair almost anything made out of. Composite. Uh, but this is a big problem because, uh, if GE does walk away and they’re talking about walking away from this project at the end of April, vineyard, wind believes that the turbines are not ready to be operated, and they d